Skip to main content

Home/ Open Intelligence / Energy/ Group items tagged construction

Rss Feed Group items tagged

D'coda Dcoda

Department of Energy Loan Guarantee Program to be discussed at Nuclear Summit [25Jul11] - 0 views

  • The conference is the 3rd Annual Nuclear Construction Summit and has already generated masses of interest from major utilities and key organisations in the USA and globally. The meeting comes at a truly critical time for the nuclear renaissance in North America.
  • Dave Frantz will join key representatives from the NRC, Duke, Dominion, Progress Energy, SCANA, OPG, Bruce Power, USEC, Areva NP, Westinghouse and many other key organisations in the nuclear industry. This year’s conference will discuss how companies can develop a strong nuclear strategy based on experience from key construction projects that mitigates risk and reduces project costs. The meeting promises to be the key construction meeting for the industry in 2011 with 300+ senior level executives involved in nuclear construction expected across the 3 days. Event organiser Nuclear Energy Insider stated “This conference has come at a hugely important time for the nuclear industry in North America. With knowledge-sharing from all of the key construction projects across the region, the meeting will be an essential platform to discuss best practice and ensure that the industry approaches future challenges head-on.”
  • For more information on the 3rd Annual Nuclear Construction Summit which is taking place in Charlotte, North Carolina on October 25-27 visit http://www.nuclearenergyinsider.com/nuclear-construction-summit
D'coda Dcoda

TVA (Tennessee Valley Authority) progresses with mPower project [17Jun11] - 0 views

  • Generation mPower (GmP) - a partnership between Babcock & Wilcox (B&W) and Bechtel - has signed a letter of intent with the Tennessee Valley Authority (TVA) which defines the project plans for constructing up to six small modular reactors (SMRs) at a site in Tennessee.  
  • In June 2009, B&W announced plans to develop and deploy a scalable, modular nuclear power reactor. The 125 MWe mPower design is an integral PWR designed to be factory-made and railed to site. B&W and Bechtel later entered into a formal alliance to design, license and deploy the design.
  • In its latest Integrated Resource Plan and associated Environmental Impact Statement, published in March 2011, TVA said that it had identified its Clinch River Breeder Reactor site at Oak Ridge, Tennessee, as a potential site for an mPower plant. Studies of the site’s suitability, including environmental issues, were due to begin in late 2010.   The Clinch River Breeder Reactor project was a joint effort of the US government and the country’s electric power industry to design and construct a sodium-cooled fast-neutron nuclear reactor. The project, first authorized in 1970, was terminated in 1983.   The letter of intent signed by GmP and TVA defines the project plans and associated conditions for designing, licensing and constructing up to six mPower units at the Clinch River site. The project is expected to include joint development and pursuit of a construction licence from the US Nuclear Regulatory Commission (NRC). The project would also include engineering, procurement and construction (EPC) activities leading to receipt of an operating licence from the NRC, assuming certain preconditions are met.
  • ...1 more annotation...
  • The letter of intent also specifies the division of responsibilities between GmP and TVA for the preparation and NRC review of a construction licence application. The letter also describes the timing of the projects activities for successful completion of major EPC milestones.   Ali Azad, GmP president and CEO, said, "We have been working with TVA for some time to evaluate the technical and regulatory requirements associated with constructing B&W mPower SMRs at its Clinch River site."   In a statement, B&W said, "GmP remains on track to deploy the first B&W mPower reactor by 2020 at TVA's Clinch River site."   The mPower Integrated System Test (IST) facility in Virginia is expected to soon begin a three-year project to collect data to verify the reactor design and safety performance in support of B&W’s licensing activities with the NRC. TVA plans to submit a construction permit application to the NRC in 2012, while GmP plans to submit a design certification application in 2013.   B&W claims that the "scalable nature of nuclear power plants built around the B&W mPower reactor would provide customers with practical power increments of 125 MWe to meet local energy needs within power grid and plant site constraints."
D'coda Dcoda

U.S. to restart construction of nuclear reactors [28Nov11] - 0 views

  • After 34 years, the United States is expected to resume construction of nuclear reactors by the end of the year, and Toshiba will export turbine equipment for the reactors to the U.S. early next month, it was learned Saturday. According to sources, construction will begin by year-end on the Nos. 3 and 4 reactors of the Alvin W. Vogtle Electric Generating Plant in Georgia Georgia Country Georgia /ˈdʒɔrdʒə/ (Georgian: საქართველო, sak’art’velo IPA: [sɑkʰɑrtʰvɛlɔ] ( listen)) is a sovereign state in the Caucasus region of Eurasia. Located at the crossroads of Western Asia and Eastern E... View full Dossier Latest news and the Nos. 2 and 3 reactors of the Virgil C. Summer Nuclear Generating Station in South Carolina South Carolina U.S. state South Carolina /ˌsaʊθ kærəˈlaɪnə/ is a state in the Deep South of the United States that borders Georgia to the south, North Carolina to the north, and the Atlantic Ocean to the east. Originally pa... View full Dossier Latest news .
  • The U.S. Nuclear Regulatory Commission Nuclear Regulatory Commission Government Agency (United States of America) The Nuclear Regulatory Commission (NRC) is an independent agency of the United States government that was established by the Energy Reorganization Act of 1974 from the United States Atomic Energy C... View full Dossier Latest news is expected to shortly approve the construction and operation of the reactors, which have been designed by Westinghouse, a subsidiary of Toshiba. The decision to resume construction of reactors is expected to pave the way for Japan Japan Country Japan /dʒəˈpæn/ (Japanese: 日本 Nihon or Nippon; formally 日本国  Nippon-koku or Nihon-koku, literally, the State of Japan) is an island nation in East Asia. Located in the Pacific Ocean, it lies to the... View full Dossier Latest news to export related equipment to the United States, observers said.
  • The reactors to be constructed are of the AP1000 type
D'coda Dcoda

India Starts Construction of New Nuclear Power Plants [18Jul11] - 0 views

  • Reactors are scheduled to be completed in the year 2016-17 Nuclear Power Corp. of India Ltd's (NPCIL) second pair of 700 MW Pressurized Heavy Water Reactors (PHWRs) – RAPP-7&8 (Rajasthan Atomic Power Project- 7&8) – achieved first pour of concrete last week at Rawatbhata in Rajasthan, India. The First Pour of Concrete (FPC) is an important milestone in the construction of a nuclear power project and signifies the start of the construction (zero date). The reactors are scheduled to be completed in the year 2016-17. On their completion, 1400 MW capacity will be added to the Northern Electricity Grid, of which 700 MW will be allocated to the state of Rajasthan. Designed in India, the 700-MW PHWR is the latest nuclear power reactor, which has been designed by NPCIL by scaling up its 540-MW PHWRs (TAPS-3&4) that are under successful operation at Tarapur in Maharashtra since 2005. Two more 700-MW PHWRs are also under construction at Kakrapar in Gujarat.
  • The 700-MW PHWRs have advanced safety features, including passive safety systems that work on natural principles like gravity, natural convection, etc. and do not need operator intervention or motive power to ensure reactor safety under any state of operation.
  • There are two independent and diverse systems to shut down the reactor, a ‘Passive Decay Heat Removal System’ to ensure cooling of the reactor core even in conditions of total loss of power, and steel-lined inner containment to contain the entire radioactivity within the reactor building even in a severe accident scenario
  • ...1 more annotation...
  • Currently, there are 20 nuclear power reactors with a capacity of 4780 MW in operation and 7 reactors with a capacity of 5300 MW under construction in the country. On progressive completion of these reactors, the installed nuclear power capacity will reach 10080 MW by the year 2017. More reactors are planned to take the installed capacity to 20000 MW or more by the year 2020.
D'coda Dcoda

Post-Fukushima, Nuclear Power Changes Latitudes - [28Nov11] - 0 views

  • As the full cost of the Fukushima nuclear accident continues to climb—Japanese officials now peg it at $64 billion or more—nuclear power’s future is literally headed south. Developed countries are slowing or shuttering their nuclear-power programs, while states to their south, in the world’s hotspots (think the Middle East and Far East), are pushing to build reactors of their own. Normally, this would lead to even more of a focus on nuclear safety and nonproliferation. Yet, given how nuclear-reactor sales have imploded in the world’s advanced economies, both these points have been trumped by nuclear supplier states’ desires to corner what reactor markets remain.
  • This spring, Germany permanently shut down eight of its reactors and pledged to shutter the rest by 2022. Shortly thereafter, the Italians voted overwhelmingly to keep their country nonnuclear. Switzerland and Spain followed suit, banning the construction of any new reactors. Then Japan’s prime minister killed his country’s plans to expand its reactor fleet, pledging to reduce Japan’s reliance on nuclear power dramatically. Taiwan’s president did the same. Now Mexico is sidelining construction of 10 reactors in favor of developing natural-gas-fired plants, and Belgium is toying with phasing its nuclear plants out, perhaps as early as 2015.
  • China—nuclear power’s largest prospective market—suspended approvals of new reactor construction while conducting a lengthy nuclear-safety review. Chinese nuclear-capacity projections for the year 2020 subsequently tumbled by as much as 30 percent. A key bottleneck is the lack of trained nuclear technicians: to support China’s stated nuclear-capacity objectives, Beijing needs to graduate 6,000 nuclear experts a year. Instead, its schools are barely generating 600.
  • ...7 more annotations...
  • India, another potential nuclear boom market, is discovering a different set of headaches: effective local opposition, growing national wariness about foreign nuclear reactors, and a nuclear liability controversy that threatens to prevent new reactor imports. India was supposed to bring the first of two Russian-designed reactors online this year in tsunami-prone Tamil Nadu state. Following Fukushima, though, local residents staged a series of starvation strikes, and the plant’s opening has now been delayed. More negative antinuclear reactions in the nearby state of West Bengal forced the local government to pull the plug on a major Russian project in Haripur. It’s now blocking an even larger French reactor-construction effort at Jaitapur.
  • These nuclear setbacks come as Prime Minister Manmohan Singh is straining to reconcile India’s national nuclear-accident-liability legislation with U.S. demands that foreign reactor vendors be absolved of any responsibility for harm that might come to property or people outside of a reactor site after an accident
  • n the United States, new-reactor construction has also suffered—not because of public opposition but because of economics
  • persuade his Parliament to cap foreign vendors’ liability to no more than $300 million (even though Japan has pegged Fukushima damages at no less than $64 billion).
  • The bottom line is that in 2007, U.S. utilities applied to the Nuclear Regulatory Commission to build 28 nuclear-power plants before 2020; now, if more than three come online before the end of the decade, it will be a major accomplishment.
  • France—per capita, the world’s most nuclear-powered state. Frequently heralded as a nuclear commercial model for the world, today it’s locked in a national debate over a partial nuclear phaseout.
  • his Socialist opponent, François Hollande, now well ahead in the polls, has proposed cutting nuclear power’s contribution to the electrical grid by more than a third by 2025. Hollande is following a clear shift in French public opinion, from two thirds who backed nuclear power before Fukushima to 62 percent who are now favoring a progressive phaseout. In addition, the French courts just awarded Greenpeace €1.5 million against the French nuclear giant EDF for illegally spying on the group. Public support of this judgment and the French Socialist Party’s wooing of the French Greens makes the likelihood of Hollande backing off his pledge minuscule.
  •  
    long article with 2 more pages (not highlighted)
D'coda Dcoda

Japan's Nukes Following Earthquake - 1 views

  • TEPCO has just released "diaries" from early in the accident giving us a better view of the sequence of events from the operators point of view.
  • The bulk of the materials, distributed on discs with digital files, show reams of raw numerical data. They include photos of broadsheet computer printouts and other formatted charts with thousands of data points for measurements of reactor heat, pressure, water levels, fuel rod positions and the status of cooling pumps, among other functions. Tokyo Electric, or Tepco, also released a smaller batch of more recent documents highlighting its various efforts to restore electric power to each of the reactors, a task that was achieved on April 26. But a series of what Tepco terms reactor "diaries" from the first 48 hours after the quake include the most visually arresting materials. These feature snapshots of whiteboards on which plant employees—11 of whom remained in each of the plant's three control rooms—jotted down status updates on the progress of the reactor shutdowns and steadily increasing radiation levels around the facility.
  • Using red, black or blue ink markers, the plant operators appear to have scribbled down the notes quickly. Many are smudged or illegible. Others depict complex diagrams and are peppered with technical jargon or acronyms such as SBO for "station blackout." http://online.wsj.com/article/SB10001424052748704281504576329011846064194.html
  • ...11 more annotations...
  • The Nuclear and Industrial Safety Agency (NISA) on June 6 revised the level of radioactivity of materials emitted from the crisis hit Fukushima No. 1 Nuclear Power Plant from 370,000 terabecquerels to 850,000 terabecquerels. (from 10,000,000 curies to 22,972,972.97 curies)http://mdn.mainichi.jp/mdnnews/news/20110606p2a00m0na009000c.html
  • Lots of interesting information in this paper from TEPCO:http://www.tepco.co.jp/en/nu/fukushima-np/images/handouts_110525_01-e.pdfUnits 1-4 did not have RCIC.  They had isolation condensers.  Not only that, the isolation condensers were water cooled with 8 hours of water in the condenser reservoir. 
  • HPCI required DC power to operate.  The turbine lube oil pump was DC; it didn't have a shaft oil pump.  I think this may be common here too, anyone willing to verify that?That's why they had trouble so quick:  8 hours later and without AC power they had no way to get water to the pressure vessel.  About the same time the instruments died from a lack of battery power is about the time they lost the isolation condenser from a lack of water.They also verify that they didn't have the hardened vent modification.
  • Fukushima may have a group that could tackle the nuclear crisis looming over Japan. The Skilled Veterans Corps, retired engineers and professionals, want to volunteer to work in the dangerous conditions instead of putting younger generations at risk. More than 200 Japanese retirees are seeking to replace younger workers at Fukushima while the plant is being stabilized. http://www.digitaljournal.com/article/307378
  • So helpless were the plant's engineers that, as dusk fell after Japan's devastating March 11 quake and tsunami, they were forced to scavenge flashlights from nearby homes. They pulled batteries from cars not washed away by the tsunami in a desperate effort to revive reactor gauges that weren't working properly. The plant's complete power loss contributed to a failure of relief vents on a dangerously overheating reactor, forcing workers to open valves by hand.And in a significant miscalculation: At first, engineers weren't aware that the plant's emergency batteries were barely working, the investigation found—giving them a false impression that they had more time to make repairs. As a result, nuclear fuel began melting down hours earlier than previously assumed. This week Tokyo Electric Power Co., or Tepco, confirmed that one of the plant's six reactors suffered a substantial meltdown early in Day 1. http://online.wsj.com/article/SB10001424052748704322804576302553455643510.html
  • The following article focus's on US spent fuel storage safety, Several members of Congress are calling for the fuel to be moved from the pools into dry casks at a faster clip, noting that the casks are thought to be capable of withstanding an earthquake or a plane crash, they have no moving parts and they require no electricity. but there is a reference to Fukishima's dry storage casks farther into the article.But Robert Alvarez, a former senior adviser to the secretary of energy and expert on nuclear power, points out that unlike the fuel pools, dry casks survived the tsunami at Fukushima unscathed. “They don’t get much attention because they didn’t fail,” he said.http://www.nytimes.com/2011/07/06/business/energy-environment/06cask.html?_r=2&pagewanted=1&ref=science
  • In 1967, Tepco chopped 25 meters off the 35-meter natural seawall where the reactors were to be located, according to documents filed at the time with Japanese authorities. That little-noticed action was taken to make it easier to ferry equipment to the site and pump seawater to the reactors. It was also seen as an efficient way to build the complex atop the solid base of bedrock needed to better protect the plant from earthquakes.But the razing of the cliff also placed the reactors five meters below the level of 14- to 15-meter tsunami hitting the plant March 11, triggering a major nuclear disaster resulting in the meltdown of three reactor cores.http://online.wsj.com/article/SB10001424052702303982504576425312941820794.html
  • Toyota was a key executive who was involved in the Fukushima No. 1 plant construction.It is actually common practice to build primary nuclear plant facilities directly on bedrock because of the temblor factor.Toyota also cited two other reasons for Tepco clearing away the bluff — seawater pumps used to provide coolant water needed to be set up on the ground up to 10 meters from the sea, and extremely heavy equipment, including the 500-ton reator pressure vessels, were expected to be brought in by boat.In fact, Tepco decided to build the plant on low ground based on a cost-benefit calculation of the operating costs of the seawater pumps, according to two research papers separately written by senior Tepco engineers in the 1960s.
  • If the seawater pumps were placed on high ground, their operating costs would be accordingly higher."We decided to build the plant at ground level after comparing the ground construction costs and operating costs of the circulation water pumps," wrote Hiroshi Kaburaki, then deputy head of the Tepco's construction office at the Fukushima No. 1 plant, in the January 1969 edition of Hatsuden Suiryoku, a technical magazine on power plants.Still, Tepco believed ground level was "high enough to sufficiently secure safety against tsunami and typhoon waves," wrote Seiji Saeki, then civil engineering section head of Tepco's construction office, in his research paper published in October 1967.
  • Engineers at Tohoku Electric Power Co., on the other hand, had a different take on the tsunami threat when the Onagawa nuclear plant was built in Miyagi Prefecture in the 1980s.Like Fukushima, the plant was built along the Tohoku coast and was hit by tsunami as high as 13 meters on March 11.Before building the plant, Tohoku Electric, examining historic records of tsunami reported in the region, conducted computer simulations and concluded the local coast could face tsumani of up to 9.1 meters.Tohoku Electric had set the construction ground level at 14.8 meters above sea level — which barely spared the Onagawa plant from major damage from 13-meter-high tsunami that hit in March.
  • Former Tepco worker Naganuma said many locals now feel they have been duped by Tepco's long-running propaganda on the safety of its nuclear facilities, despite the huge economic benefits the plant brought to his hometown of Okuma, which hosts the Fukushima No. 1 plant.
  •  
    from a nuclear worker's forum so the dates run from May 20, 2011 to July 15, 2011...these are the points these nuclear workers thought important about Fukushima
D'coda Dcoda

The nuclear power plans that have survived Fukushima [28Sep11] - 0 views

  • SciDev.Net reporters from around the world tell us which countries are set on developing nuclear energy despite the Fukushima accident. The quest for energy independence, rising power needs and a desire for political weight all mean that few developing countries with nuclear ambitions have abandoned them in the light of the Fukushima accident. Jordan's planned nuclear plant is part of a strategy to deal with acute water and energy shortages.
  • The Jordan Atomic Energy Commission (JAEC) wants Jordan to get 60 per cent of its energy from nuclear by 2035. Currently, obtaining energy from neighbouring Arab countries costs Jordan about a fifth of its gross domestic product. The country is also one of the world's most water-poor nations. Jordan plans to desalinate sea water from the Gulf of Aqaba to the south, then pump it to population centres in Amman, Irbid, and Zarqa, using its nuclear-derived energy. After the Fukushima disaster, Jordan started re-evaluating safety procedures for its nuclear reactor, scheduled to begin construction in 2013. The country also considered more safety procedures for construction and in ongoing geological and environmental investigations.
  • The government would not reverse its decision to build nuclear reactors in Jordan because of the Fukushima disaster," says Abdel-Halim Wreikat, vice Chairman of the JAEC. "Our plant type is a third-generation pressurised water reactor, and it is safer than the Fukushima boiling water reactor." Wreikat argues that "the nuclear option for Jordan at the moment is better than renewable energy options such as solar and wind, as they are still of high cost." But some Jordanian researchers disagree. "The cost of electricity generated from solar plants comes down each year by about five per cent, while the cost of producing electricity from nuclear power is rising year after year," says Ahmed Al-Salaymeh, director of the Energy Centre at the University of Jordan. He called for more economic feasibility studies of the nuclear option.
  • ...20 more annotations...
  • And Ahmad Al-Malabeh, a professor in the Earth and Environmental Sciences department of Hashemite University, adds: "Jordan is rich not only in solar and wind resources, but also in oil shale rock, from which we can extract oil that can cover Jordan's energy needs in the coming years, starting between 2016 and 2017 ... this could give us more time to have more economically feasible renewable energy."
  • Finance, rather than Fukushima, may delay South Africa's nuclear plans, which were approved just five days after the Japanese disaster. South Africa remains resolute in its plans to build six new nuclear reactors by 2030. Katse Maphoto, the director of Nuclear Safety, Liabilities and Emergency Management at the Department of Energy, says that the government conducted a safety review of its two nuclear reactors in Cape Town, following the Fukushima event.
  • The Ninh Thuan nuclear plant would sit 80 to 100 kilometres from a fault line on the Vietnamese coast, potentially exposing it to tsunamis, according to state media. But Vuong Huu Tan, president of the state-owned Vietnam Atomic Energy Commission, told state media in March, however, that lessons from the Fukushima accident will help Vietnam develop safe technologies. And John Morris, an Australia-based energy consultant who has worked as a geologist in Vietnam, says the seismic risk for nuclear power plants in the country would not be "a major issue" as long as the plants were built properly. Japan's nuclear plants are "a lot more earthquake prone" than Vietnam's would be, he adds.
  • Larkin says nuclear energy is the only alternative to coal for generating adequate electricity. "What other alternative do we have? Renewables are barely going to do anything," he said. He argues that nuclear is capable of supplying 85 per cent of the base load, or constantly needed, power supply, while solar energy can only produce between 17 and 25 per cent. But, despite government confidence, Larkin says that a shortage of money may delay the country's nuclear plans.
  • The government has said yes but hasn't said how it will pay for it. This is going to end up delaying by 15 years any plans to build a nuclear station."
  • Vietnam's nuclear energy targets remain ambitious despite scientists' warning of a tsunami risk. Vietnam's plan to power 10 per cent of its electricity grid with nuclear energy within 20 years is the most ambitious nuclear energy plan in South-East Asia. The country's first nuclear plant, Ninh Thuan, is to be built with support from a state-owned Russian energy company and completed by 2020. Le Huy Minh, director of the Earthquake and Tsunami Warning Centre at Vietnam's Institute of Geophysics, has warned that Vietnam's coast would be affected by tsunamis in the adjacent South China Sea.
  • Undeterred by Fukushima, Nigeria is forging ahead with nuclear collaborations. There is no need to panic because of the Fukushima accident, says Shamsideen Elegba, chair of the Forum of Nuclear Regulatory Bodies in Africa. Nigeria has the necessary regulatory system to keep nuclear activities safe. "The Nigerian Nuclear Regulatory Authority [NNRA] has established itself as a credible organisation for regulatory oversight on all uses of ionising radiation, nuclear materials and radioactive sources," says Elegba who was, until recently, the NNRA's director general.
  • Vietnam is unlikely to experience much in the way of anti-nuclear protests, unlike neighbouring Indonesia and the Philippines, where civil society groups have had more influence, says Kevin Punzalan, an energy expert at De La Salle University in the Philippines. Warnings from the Vietnamese scientific community may force the country's ruling communist party to choose alternative locations for nuclear reactors, or to modify reactor designs, but probably will not cause extreme shifts in the one-party state's nuclear energy strategy, Punzalan tells SciDev.Net.
  • But the government adopted its Integrated Resource Plan (IRP) for 2010-2030 five days after the Fukushima accident. Elliot Mulane, communications manager for the South African Nuclear Energy Corporation, (NECSA) a public company established under the 1999 Nuclear Energy Act that promotes nuclear research, said the timing of the decision indicated "the confidence that the government has in nuclear technologies". And Dipuo Peters, energy minister, reiterated the commitment in her budget announcement earlier this year (26 May), saying: "We are still convinced that nuclear power is a necessary part of our strategy that seeks to reduce our greenhouse gas emissions through a diversified portfolio, comprising some fossil-based, renewable and energy efficiency technologies". James Larkin, director of the Radiation and Health Physics Unit at the University of the Witwatersrand, believes South Africa is likely to go for the relatively cheap, South Korean generation three reactor.
  • In the meantime, the government is trying to build capacity. The country lacks, for example, the technical expertise. Carmencita Bariso, assistant director of the Department of Energy's planning bureau, says that, despite the Fukushima accident, her organisation has continued with a study on the viability, safety and social acceptability of nuclear energy. Bariso says the study would include a proposal for "a way forward" for the Bataan Nuclear Power Plant, the first nuclear reactor in South East Asia at the time of its completion in 1985. The $2.3-billion Westinghouse light water reactor, about 60 miles north of the capital, Manila, was never used, though it has the potential to generate 621 megawatts of power. President Benigno Aquino III, whose mother, President Corazon Aquino, halted work on the facility in 1986 because of corruption and safety issues, has said it will never be used as a nuclear reactor but could be privatised and redeveloped as a conventional power plant.
  • But Mark Cojuangco, former lawmaker, authored a bill in 2008 seeking to start commercial nuclear operations at the Bataan reactor. His bill was not passed before Congress adjourned last year and he acknowledges that the Fukushima accident has made his struggle more difficult. "To go nuclear is still the right thing to do," he says. "But this requires a societal decision. We are going to spark public debates with a vengeance as soon as the reports from Fukushima are out." Amended bills seeking both to restart the reactor, and to close the issue by allowing either conversion or permanent closure, are pending in both the House and the Senate. Greenpeace, which campaigns against nuclear power, believes the Fukushima accident has dimmed the chances of commissioning the Bataan plant because of "increased awareness of what radioactivity can do to a place". Many parts of the country are prone to earthquakes and other natural disasters, which critics say makes it unsuitable both for the siting of nuclear power stations and the disposal of radioactive waste.
  • In Kenya, nuclear proponents argue for a geothermal – nuclear mix In the same month as the Fukushima accident, inspectors from the International Atomic Energy Agency approved Kenya's application for its first nuclear power station (31 March), a 35,000 megawatt facility to be built at a cost of Sh950 billion (US$9.8 billion) on a 200-acre plot on the Athi Plains, about 50km from Nairobi
  • The plant, with construction driven by Kenya's Nuclear Electricity Project Committee, should be commissioned in 2022. The government claims it could satisfy all of Kenya's energy needs until 2040. The demand for electricity is overwhelming in Kenya. Less than half of residents in the capital, Nairobi, have grid electricity, while the rural rate is two per cent. James Rege, Chairman of the Parliamentary Committee on Energy, Communication and Information, takes a broader view than the official government line, saying that geothermal energy, from the Rift Valley project is the most promising option. It has a high production cost but remains the country's "best hope". Nuclear should be included as "backup". "We are viewing nuclear energy as an alternative source of power. The cost of fossil fuel keeps escalating and ordinary Kenyans can't afford it," Rege tells SciDev.Net.
  • Hydropower is limited by rivers running dry, he says. And switching the country's arable land to biofuel production would threaten food supplies. David Otwoma, secretary to the Energy Ministry's Nuclear Electricity Development Project, agrees that Kenya will not be able to industrialise without diversifying its energy mix to include more geothermal, nuclear and coal. Otwoma believes the expense of generating nuclear energy could one day be met through shared regional projects but, until then, Kenya has to move forward on its own. According to Rege, much as the nuclear energy alternative is promising, it is extremely important to take into consideration the Fukushima accident. "Data is available and it must be one step at a time without rushing things," he says. Otwoma says the new nuclear Kenya can develop a good nuclear safety culture from the outset, "but to do this we need to be willing to learn all the lessons and embrace them, not forget them and assume that won't happen to us".
  • Will the Philippines' plans to rehabilitate a never-used nuclear power plant survive the Fukushima accident? The Philippines is under a 25-year moratorium on the use of nuclear energy which expires in 2022. The government says it remains open to harnessing nuclear energy as a long-term solution to growing electricity demand, and its Department of Science and Technology has been making public pronouncements in favour of pursuing nuclear energy since the Fukushima accident. Privately, however, DOST officials acknowledge that the accident has put back their job of winning the public over to nuclear by four or five years.
  • It is not only that we say so: an international audit came here in 2006 to assess our procedure and processes and confirmed the same. Elegba is firmly of the view that blame for the Fukushima accident should be allocated to nature rather than human error. "Japan is one of the leaders not only in that industry, but in terms of regulatory oversight. They have a very rigorous system of licensing. We have to make a distinction between a natural event, or series of natural events and engineering infrastructure, regulatory infrastructure, and safety oversight." Erepamo Osaisai, Director General of the Nigeria Atomic Energy Commission (NAEC), has said there is "no going back" on Nigeria's nuclear energy project after Fukushima.
  • Nigeria is likely to recruit the Russian State Corporation for Atomic Energy, ROSATOM, to build its first proposed nuclear plant. A delegation visited Nigeria (26- 28 July) and a bilateral document is to be finalised before December. Nikolay Spassy, director general of the corporation, said during the visit: "The peaceful use of nuclear power is the bedrock of development, and achieving [Nigeria's] goal of being one of the twenty most developed countries by the year 2020 would depend heavily on developing nuclear power plants." ROSATOM points out that the International Atomic Energy Agency monitors and regulates power plant construction in previously non-nuclear countries. But Nnimmo Bassey, executive director of the Environmental Rights Action/Friends of the Earth Nigeria (ERA/FoEN), said "We cannot see the logic behind the government's support for a technology that former promoters in Europe, and other technologically advanced nations, are now applying brakes to. "What Nigeria needs now is investment in safe alternatives that will not harm the environment and the people. We cannot accept the nuclear option."
  • Thirsty for electricity, and desirous of political clout, Egypt is determined that neither Fukushima ― nor revolution ― will derail its nuclear plans. Egypt was the first country in the Middle East and North Africa to own a nuclear programme, launching a research reactor in 1961. In 2007 Egypt 'unfroze' a nuclear programme that had stalled in the aftermath of the Chernobyl disaster. After the Egyptian uprising in early 2011, and the Fukushima accident, the government postponed an international tender for the construction of its first plant.
  • Yassin Ibrahim, chairman of the Nuclear Power Plants Authority, told SciDev.Net: "We put additional procedures in place to avoid any states of emergency but, because of the uprising, the tender will be postponed until we have political stability after the presidential and parliamentary election at the end of 2011". Ibrahim denies the nuclear programme could be cancelled, saying: "The design specifications for the Egyptian nuclear plant take into account resistance to earthquakes and tsunamis, including those greater in magnitude than any that have happened in the region for the last four thousand years. "The reactor type is of the third generation of pressurised water reactors, which have not resulted in any adverse effects to the environment since they began operation in the early sixties."
  • Ibrahim El-Osery, a consultant in nuclear affairs and energy at the country's Nuclear Power Plants Authority, points out that Egypt's limited resources of oil and natural gas will run out in 20 years. "Then we will have to import electricity, and we can't rely on renewable energy as it is still not economic yet — Egypt in 2010 produced only two per cent of its needs through it." But there are other motives for going nuclear, says Nadia Sharara, professor of mineralogy at Assiut University. "Owning nuclear plants is a political decision in the first place, especially in our region. And any state that has acquired nuclear technology has political weight in the international community," she says. "Egypt has the potential to own this power as Egypt's Nuclear Materials Authority estimates there are 15,000 tons of untapped uranium in Egypt." And she points out it is about staying ahead with technology too. "If Egypt freezes its programme now because of the Fukushima nuclear disaster it will fall behind in many science research fields for at least the next 50 years," she warned.
D'coda Dcoda

Atomic Energy Council blamed for neglecting regulatory duties -Taiwan [14Sep11] - 0 views

  • Taipei, Sept. 14 (CNA) Shih Hsin-min, founding chairman of Taiwan Environmental Protection Union (TEPU), criticized the Cabinet-level Atomic Energy Council (AEC) Wednesday for failing to play its role as the country's nuclear safety supervisor.
  • The top authority governing nuclear energy affairs should not be "the player and judge," -- promoting nuclear energy and at the same time overseeing nuclear safety -- because the council has never done the regulatory job well, Shih said. The activist also charged that the recent resignation spree among members of the AEC-operated Fourth Nuclear Power Plant Safety Oversight Committee is "not even a second thought" for the council, because to the AEC, the committee is nothing more than an advisory body
  • "Any resolution of the committee is merely a reference for the AEC minister," he said in response to AEC Deputy Minister Shieh Der-jhy's resignation from both the post and the position as chairman of the nuclear power plant safety oversight committee, as well as the resignation of Lin Tsung-yao, a member of the committee. Shieh's resignation took effect on Sept. 1. As for Lin, AEC Minister Tsai Chuen-horng is trying to persuade the veteran nuclear safety advocate, who had served as an engineer at General Electric Co., from leaving, AEC officials said.
  • ...3 more annotations...
  • The two resignations came after a meeting of the AEC committee on July 29, in which Lin presented a 5,000-word report on the ongoing construction of the planned Fourth Nuclear Power Plant in Gongliao District of New Taipei City, northern Taiwan. Lin warned in the report, written in Chinese, that the construction project has many structural flaws, including those in the unique digital control system which employs nearly 40,000 signal detectors.
  • The way its builder, the state-run Taiwan Power Company (Taipower), has hired contractors was also "unique," Lin said, revealing that many of the contractors have never built nuclear power plants. At the construction site, supervision almost did not exist, he added. Furthermore, h
  • Construction of the Fourth Nuclear Power Plant began in 1999. It was scheduled to begin commercial operations before the end of 2011 but Taipwer has announced the commercial run won't be possible until 2012. Lin's report led the July meeting to produce a resolution that the construction mu
D'coda Dcoda

Nuclear generation rise in 2010 [15Jun11] - 0 views

  • The total amount of electricity generated by nuclear powers plants around the world increased in 2010 following three consecutive years of decline. However, a sharp drop in output is foreseen for 2011 as a result of the Fukushima accident.    Global nuclear electricity generation in 2010 totalled 2630 TWh, according to figures from the International Atomic Energy Agency (IAEA), representing a 2.8% increase from the 2558 TWh generated in 2009 and taking it close to a peak value in 2006. The energy availability factor of the plants operating in 2010 was 81%, up from 79.4% in 2009.
  • New reactors amounting to 3722 MWe net boosted the 2010 figure, including Russia's Rostov 2, India's Rajasthan 6, China's Ling Ao 3 and Qinshan II-3, and South Korea's Shin Kori 1.   Just one small reactor - France's 130 MWe Phenix prototype fast reactor - was officially shut down in 2010, although the unit actually ceased power generation in 2009.
  • Construction of 16 new reactors, with a combined capacity of 15,846 MWe net, started in 2010, according to the IAEA. Ten of these are in China (Ningde units 3 and 4, Taishan 2, Changjiang 1 and 2, Haiyang 2, Fangchenggang 1 and 2, Yangjiang 3 and Fuqing 3). In Russia, the construction of two new units also began (Leningrad II unit 2 and Rostov 4), while two more started construction in India (Kakrapar 3 and 4). In Brazil, work also started on building the Angra 3 unit. Meanwhile, the stalled construction of Japan's 1383 MWe Ohma unit also got back underway in 2010 after re-engineering work for enhanced earthquake protection.
  • ...4 more annotations...
  • Despite a return to form for nuclear power in 2010, the impact of the Fukushima accident, not only in Japan but around the world, will significantly reduce the amount of electricity generated by nuclear power plants in 2011.
  • Fukushima impact
  • Assuming about five years for construction it can be expected that reactors will be coming online around 2012 at double today's rate of five per year, with this to rise to one per month around 2015.
  • According to data released by the Japan Atomic Industry Forum (JAIF), only 17 of Japan's 54 nuclear power reactors were in operation in mid-May. They represented around 15,500 MWe, or 31%, of the country's total nuclear generating capacity.
D'coda Dcoda

PM hints at approval for some nuclear reactors under construction - Japan [18... - 0 views

  • Prime Minister Yoshihiko Noda has suggested that he will give the green light to operations of some nuclear reactors under construction. “The construction of some nuclear power plants has progressed to a great extent. I’ll make a final decision on each of them while considering the opinions of the local communities,” Noda said in an interview with the Mainichi Shimbun and other media organizations at his office on Oct. 17. He apparently made the remarks while keeping in mind the No. 3 reactor at the Shimane Nuclear Power Plant, 90 percent of whose construction work has been finished. Noda had told a news conference when he took office that it would be difficult to install new nuclear reactors.
D'coda Dcoda

New Reactor in Tennessee: Safety Concerns Cloud US Nuclear Renaissance [22Jul11] - 0 views

  • Watts Bar 2, the US's newest nuclear power plant, is being built in Tennessee and is expected to go online next year. It has a history of safety concerns that goes back decades. Nevertheless, many local people support nuclear power and are welcoming the reactor with open arms.
  • Mansour Guity was the chief witness against the American nuclear industry. He crippled entire power plants almost single-handedly. But now the 30-year war he has been waging is coming to an end. They are now putting the finishing touches on the second reactor at the Watts Bar Nuclear Generating Station in the Tennessee River valley, less than 50 kilometers (31 miles) from Guity's house. After construction was stopped more than two decades ago and resumed in 2007, the reactor is now expected to go online next year. Mansour Guity isn't doing too well at the moment.
  • In the 1960s, 1970s and 1980s, he gradually discovered that so many shortcuts were taken, and some of the work was so shoddy, during the construction of the nuclear plants along the Tennessee River that it made a mockery of any notion of nuclear safety. Guity was a nuclear engineer at the Tennessee Valley Authority (TVA), a large, long-established government-owned company that operates the Browns Ferry, Sequoyah, Bellefonte and Watts Bar nuclear power plants. When the plants were built, there was talk of thousands of clear violations of plans and building regulations, with the most serious infractions occurring at Watts Bar.
  • ...6 more annotations...
  • A nuclear engineer who was born in Iran in 1942, Guity is a disappointed American today. "Time bombs," he says, sounding very bitter. "We are sitting on a bunch of ticking time bombs."
  • Not Up to Standard
  • The plant's two units were built at the same time in the 1970s and 80s. Only Unit 1 was placed into operation, after a dramatic delay, while Unit 2 remained unfinished until construction was resumed a few years ago. If Guity had his way, the entire plant, including both units and everything else associated with it, would disappear from the map as soon as possible.
  • The reason Guity still has trouble sleeping at night is his belief that all of these old mistakes and violations can never be completely corrected.
  • One of the reasons Guity is so upset is that there is no public debate in the United States over Watts Bar, or nuclear energy in general. It is a non-issue throughout the country, even though, according to Guity, there are plenty of reasons that it should be discussed. The United States has 104 nuclear reactors in operation, more than any other country in the world. Many plants are alarmingly dated -- some are 40 years old or even older. Some 65,000 tons of nuclear waste have accumulated over the decades. As unbelievable as it sounds, the country doesn't even have a long-term plan for the storage and disposal of the nuclear waste being generated every day.
  • If the second unit at Watts Bar, America's last reactor still under construction, really does go online next year, almost 40 years after building work began, parts of the unit will still date from the time when so many criteria were being violated. In fact, no one, not even the TVA, knows exactly the nature and scope of these violations.
D'coda Dcoda

An Inside Look At The Current State Of The Nuclear Industry [29Sep11] - 0 views

  • As I’ve mentioned before, I’m a fan of nuclear energy.  I was able to get an inside look at the current state of the nuclear industry from a friend at Qualitech Solutions named Chris Sewell.  Qualitech Solutions provides mission-critical software to many industries, including the energy industry.  They have customers that are involved in nuclear utilities as well as design engineering firms working on major construction projects.  Qualitech Solutions has been in business for more than a decade.
  • Sewell says, “There is a hesitancy to continue with nuclear construction projects amidst the public concern over nuclear safety.  Society as a whole has become hypersensitive with anything pertaining to nuclear plant issues and safety.  The Fukushima incident not only altered the social climate, but also affected the financial backing of various new construction projects. There is however, a general consensus that due to its low carbon imprint, nuclear energy must be part of our energy future.”
  • The general public fears nuclear energy.  That is understandable considering the information that the public has been given.  The catastrophes and the mistakes are front page news.  But if the general public had more information about how the best nuclear plants are run, the opinion could turn.  This is why I asked Sewell about the success of nuclear energy in France.
  • ...2 more annotations...
  • The French generate approximately 80% of their energy using nuclear power.  They have realized the long-term financial and environmental benefits to nuclear power and have continued supporting the industry and its growth within their country and abroad.  AREVA, the French nuclear engineering firm, continues to work with partner companies to license and construct new nuclear plants and fuel facilities, such as the uranium enrichment plant in Idaho.” But in other countries, “nuclear plants are trying to get by with fewer people,” Sewell explained.  However, the more safety mechanisms that are developed in the industry, the more financial support the nuclear energy industry will receive.  One big safety development is in regard to the nuclear reactors themselves.
  • The newest nuclear reactors (Generation IIIs) have additional layers of safety and technology to stave off a meltdown in the event of a power loss (as happened at Fukushima).  The first of the Generation III reactors is due to come online in 2016 at The Vogtle Electric Generating Plant, located in Georgia,” said Sewell. The more safety measures that are developed, the more proactive the nuclear energy industry can be in addressing problem areas before a catastrophe happens.  I'm sure this won't make everyone feel safe tonight though, will it?
D'coda Dcoda

First Large Scale 24/7 Solar Power Plant to be Constructed in U.S [29Sep11] - 0 views

  • The Obama administration provided a loan guarantee of $737 million to SolarReserve on Thursday to construct the first large-scale solar power plant that stores energy and provides electricity 24 hours a day, 7 days a week. The solar power project will be constructed in Nevada. (Note that BrightSource Energy is at a similar stage in the development of a larger solar thermal power plant in the Mojave Desert, receiving a DOE loan guarantee of $1.37 billion in February 2010 and $168 million from Google this April.)
  • The SolarReserve power plant utilizes what is called thermal energy storage to store heat collected from the sun, which is then utilized by the power plant to boil water and produce steam. The steam then turns a steam turbine which generates electricity. This is a how a solar thermal power plant generally works, but keep in mind that there are different types of solar thermal power plants, some of which are not steam.
  • This type collects heat and stores it in molten salt which is then circulated to the boiler. The boiler… boils water into steam which then rushes through a steam turbine.17,500 heliostats* focus or concentrate sunlight onto the collector at the top of a 640-foot tall tower until it reaches a temperature of 1,050 degrees Fahrenheit.
  • ...1 more annotation...
  • The power plant’s electricity generation capacity (basically, how much it can generate) is 110-MW, which makes it one of the larger-scale solar power plants out there today.You might have guessed by now that this type of power plant is able to provide electricity at night, and all week, because it stores heat in the form of salt that is released in the evening so that the plant can continue to generate electricity when it is dark, cloudy, or stormy.
D'coda Dcoda

#Fukushima I Nuke Plant: TEPCO Ready to Drive Carbon-Based Workers Even Harder [11Sep11] - 0 views

  • TEPCO announced on September 9 that 6 workers entered the reactor building of Reactor 3 at Fukushima I Nuclear Power Plant, and installed a water gauge to measure the amount of contaminated water in the basement. According to the company, the radiation exposure of the 6 workers was between 0.33 to 5.26 millisieverts. The measurement using the water gauge is set to start on or after September 12.
  • ... TEPCO also disclosed the plan to start removing the debris from the upper floors of Reactors 3 and 4. The work will start in Reactor 3 on September 10, and it will start in Reactor 4 within this month. Upper floors of Reactors 3 and 4 are littered with damaged ceiling panels and exterior wall panels, and it is hoped that the spread of radioactive materials will be suppressed by removing the debris.
  • Removing the debris will stir up the radioactive materials instead of suppressing them, won't it? Not to mention exposing the workers to an inadvertent 10-plus sieverts/hour super hot spot, as it happened near the exhaust stack between Reactors 1 and 2?From the tweets by the worker at Fukushima I Nuke Plant, it is evident that TEPCO is fast running out of money (to spend on the accident, apparently not on its retiring executives) and carbon-based workers to do further work. The worker also tweeted a week or so ago that the construction people were active, already clearing debris in Reactor 4.
  • ...2 more annotations...
  • The construction companies (Kajima, Taisei are at Fukushima, I think) are the worst offenders in Japan traditionally when it comes to exploiting the temporary, contract workers. Apparently, according to the tweets by the worker mentioned above, there are workers hired by them who know little about radiation danger at Fukushima I Nuke Plant where a 10-sieverts/hr extreme hot spot can be just around the corner.Perhaps I shouldn't say "TEPCO" in the title. It is not really TEPCO who is ready and willing to expose workers to high radiation by driving them to clean up the place. TEPCO asks its main subcontractors (in this case, large construction companies) to figure out a way to complete the task of clearing the debris and tells them the budget. The subcontractors tell their subcontractors , who then tell their subcontractors....(up to 6th or 7th degree removed from TEPCO) to figure out a way, and finally some fresh warm bodies are brought in and put to work. They may or may not know the risk. The task is simple, just removing the debris from the floors with full protection gear and face mask, climbing up and down the stairs as the elevators are broken. All they need is physical strength.
  • (By the way, he also says the flashing bright light in TEPCO's livecam at night is from the construction people. Not that you have to believe him necessarily, but just for your information.)By putting in many layers of subcontracting, everyone can deny that they are willingly and actively putting workers at risk.Ah the country is broken (and broke), and mountains and rivers are not the same any more, but the subcontracting and "dango" (collusion) are hard to die in Japan.
D'coda Dcoda

Nuclear Island opens to UK students [16Jun11] - 0 views

  • UK science and engineering students will be able to experience building a scaled down nuclear power plant as part of a new training programme known as the Nuclear Island.   The programme was officially launched on 15 June, when a pilot week began with 25 engineering students from Imperial College London designing and constructing a scaled down nuclear power plant. They will be assessed in relation to real-life skills such as radiation protection, site licensing, budgetary control and project management. The pilot week is scheduled to end with a yet to be unveiled safety breach, which will test the students' ability to respond to a potential disaster scenario.
  • The Nuclear Island has been developed by a partnership of Imperial College London, Constructionarium, Cogent Sector Skills Council, the Engineering Construction Industry Training Board (ECITB) and Construction Skills. The partnership received funding to develop the project from the National Higher Education Science, Technology, Engineering and Mathematics (HE STEM) Programme and the Royal Academy of Engineers.
  • The Nuclear Island will be a hands-on new build experience for students initially in engineering, but will be broadened out to other science, technology, engineering and mathematical areas as part of the pilot programme. According to Cogent, "For the first time, nuclear safety culture will be an essential part of construction engineering courses, embedding critical safety behaviours from day one."
D'coda Dcoda

CWIP Construction Work in Progress Law - 0 views

  • CWIP, or Construction Work in Progress, is a law, fortunately existent only in a handful of U.S. states, that allows a utility to charge ratepayers higher rates to cover future costs of a yet-to-be-constructed reactor, even if that reactor is never built.
D'coda Dcoda

Skyrocketing new reactor construction costs that just toppled Calvert Cliffs ... - 0 views

  • NIRS, Public Citizen, South Carolina Sierra Club, and former NRC Commissioner Peter Bradford have warned in a press release that the same forces -- skyrocketing new reactor construction costs, decreased demand for electricity, competition from renewables and efficiency, low natural gas prices, etc. -- which just undermined the Calvert Cliffs 3 new reactor proposal in Maryland are also battering away at the new reactor proposals in Texas (South Texas Project Units 3 and 4) and South Carolina (V.C. Summer Units 2 and 3). Calvert Cliffs, South Texas Project, and Summer were the top three federal nuclear loan guarantee finalists after Vogtle Units 3 and 4 in Georgia, which the Obama administration awarded a conditional $8.3 billion taxpayer-backed loan guarantee last February. The audio recording of the full press conference is also posted online.
D'coda Dcoda

German Nuclear Decommissioning and Renewables Build-Out [23Oct11] - 0 views

  • Germany will be redirecting its economy towards renewable energy, because of the political decision to decommission its nuclear plants, triggered by the Fukushima event in Japan and subsequent public opposition to nuclear energy. Germany's decision would make achieving its 2020 CO2 emission reduction targets more difficult.   To achieve the CO2 emissions reduction targets and replace nuclear energy, renewable energy would need to scale up from 17% in 2010 to 57% of total electricity generation of 603 TWh in 2020, according to a study by The Breakthrough Institute. As electricity generation was 603 TWh in 2010, increased energy efficiency measures will be required to flat-line electricity production during the next 9 years.   Germany has 23 nuclear reactors (21.4 GW), 8 are permanently shut down (8.2 GW) and 15 (13.2 GW) will be shut down by 2022. Germany will be adding a net of 5 GW of coal plants, 5 GW of new CCGT plants and 1.4 GW of new biomass plants in future years. The CCGT plants will reduce the shortage of quick-ramping generation capacity for accommodating variable wind and solar energy to the grid.
  • Germany is planning a $14 billion build-out of transmission systems for onshore and future offshore wind energy in northern Germany and for augmented transmission with France for CO2-free hydro and nuclear energy imports to avoid any shortages.    Germany had fallen behind on transmission system construction in the north because of public opposition and is using the nuclear plant shutdown as leverage to reduce public opposition. Not only do people have to look at a multitude of 450-ft tall wind turbines, but also at thousands of 80 to 135 ft high steel structures and wires of the transmission facilities.   The $14 billion is just a minor down payment on the major grid reorganization required due to the decommissioning of the nuclear plants and the widely-dispersed build-outs of renewables. The exisitng grid is mostly large-central-plant based. 
  • This article includes the estimated capital costs of shutting down Germany's nuclear plants, reorganizing the grids of Germany and its neighbors, and building out renewables to replace the nuclear energy.    Germany’s Renewable Energy Act (EEG) in 2000, guarantees investors above-market fees for solar power for 20 years from the point of installation. In 2010, German investments in  renewables was about $41.2 billion, of which about $36.1 billion in 7,400 MW of solar systems ($4,878/kW). In 2010, German incentives for all renewables was about $17.9 billion, of which about half was for solar systems.   The average subsidy in 2010 was about ($9 billion x 1 euro/1.4 $)/12 TWh = 53.6 eurocents/kWh; no wonder solar energy is so popular in Germany. These subsidies are rolled into electric rates as fees or taxes, and will ultimately make Germany less competitive in world markets.   http://thebreakthrough.org/blog//2011/06/analysis_germanys_plan_to_phas-print.html http://mobile.bloomberg.com/news/2011-05-31/merkel-faces-achilles-heel-in-grids-to-unplug-german-nuclear.html http://www.theecologist.org/News/news_analysis/829664/revealed_how_your_country_compares_on_renewable_investment.html http://en.wikipedia.org/wiki/Solar_power_in_Germany  
  • ...12 more annotations...
  • SUMMARY OF ESTIMATED CAPITAL AND OTHER COSTS   The estimated capital costs and other costs for decommissioning the nuclear plants, restoring the sites, building out renewables, wind and solar energy balancing plants, and reorganizing electric grids over 9 years are summarized below.    The capital cost and subsidy cost for the increased energy efficiency measures was not estimated, but will likely need to be well over $180 billion over 9 years, or $20 billion/yr, or $20 b/($3286 b in 2010) x 100% = 0.6% of GDP, or $250 per person per yr.     Decommission nuclear plants, restore sites: 23 @ $1 billion/plant = $23 billion Wind turbines, offshore: 53,300 MW @ $4,000,000/MW = $213.2 billion   Wind turbines, onshore: 27,900 MW @ $2,000,000/MW = $55.8 billion Wind feed-in tariff extra costs rolled into electric rates over 9 years: $200 billion  Solar systems: 82,000 MW @ $4,500,000/MW = $369 billion Solar feed-in tariff extra costs rolled into electric rates over 9 years = $250 billion. Wind and solar energy balancing plants: 25,000 MW of CCGTs @ $1,250,000/MW = $31.3 billion Reorganizing European elecric grids tied to German grids: $150 billion
  • RENEWABLE ENERGY AND ENERGY EFFICIENCY TARGETS   In September 2010 the German government announced the following targets:   Renewable electricity - 35% by 2020 and 80% by 2050 Renewable energy - 18% by 2020, 30% by 2030, and 60% by 2050 Energy efficiency - Reducing the national electricity consumption 50% below 2008 levels by 2050.  http://en.wikipedia.org/wiki/Renewable_energy_in_Germany   Germany has a target to reduce its nation-wide CO2 emissions from all sources by 40% below 1990 levels by 2020 and 80-85% below 1990 levels by 2050. That goal could be achieved, if 100% of electricity is generated by renewables, according to Mr. Flasbarth. Germany is aiming to convince the rest of Europe to follow its lead.
  • Biomass: At the end of 2010, about 5,200 MW of biomass was installed at a capital cost of about $18 billion. Biomass energy produced was 33.5 TWh, or 5.5% of production. Plans are to add 1,400 MW of biomass plants in future years which, when fully implemented, would produce about 8.6 TWh/yr.   Solar: At the end of 2010, about 17,320 MW of PV solar was installed in Germany at a capital cost of about $100 billion. PV solar energy produced was 12 TWh, or 2% of total production. The excess cost of the feed-in-tariff energy bought by utilities and rolled into the electricity costs of rate payers was about $80 billion during the past 11 years.   Most solar panels are in southern Germany (nation-wide solar CF 0.095). When skies are clear, the solar production peaks at about 7 to 10 GW. Because of insufficient capacity of transmission and quick-ramping gas turbine plants, and because curtailment is not possible, part of the solar energy, produced at a cost to the German economy of about 30 to 50 eurocent/kWh is “sold” at European spot prices of about 5 eurocent/kWh to France which has significant hydro capacity for balancing the variable solar energy. http://theenergycollective.com/willem-post/46142/impact-pv-solar-feed-tariffs-germany  
  • Wind: At the end of 2010, about 27,200 MW of onshore and offshore wind turbines was installed in Germany at a capital cost of about $50 billion. Wind energy produced was 37.5 TWh, or 6.2% of total production. The excess cost of the feed-in-tariff energy bought by utilities and rolled into electricity costs of rate payers was about $50 billion during the past 11 years.   Most wind turbines are in northern Germany. When wind speeds are higher wind curtailment of 15 to 20 percent takes place because of insufficient transmission capacity and quick-ramping gas turbine plants. The onshore wind costs the Germany economy about 12 eurocent/kWh and the offshore wind about 24 eurocent/kWh. The owners of the wind turbines are compensated for lost production.   The alternative to curtailment is to “sell” the energy at European spot prices of about 5 eurocent/kWh to Norway and Sweden which have significant hydro capacity for balancing the variable wind energy; Denmark has been doing it for about 20 years.   As Germany is very marginal for onshore wind energy (nation-wide onshore wind CF 0.167) and nearly all of the best onshore wind sites have been used up, or are off-limits due to noise/visual/environmental impacts, most of the additional wind energy will have to come from OFFSHORE facilities which produce wind energy at about 2 to 3 times the cost of onshore wind energy. http://theenergycollective.com/willem-post/61774/wind-energy-expensive
  • A 2009 study by EUtech, engineering consultants, concluded Germany will not achieve its nation-wide CO2 emissions target; the actual reduction will be less than 30%. The head of Germany's Federal Environment Agency (UBA), Jochen Flasbarth, is calling for the government to improve CO2 reduction programs to achieve targets. http://www.spiegel.de/international/germany/0,1518,644677,00.html   GERMAN RENEWABLE ENERGY TO-DATE   Germany announced it had 17% of its electrical energy from renewables in 2010; it was 6.3% in 2000. The sources were 6.2% wind, 5.5% biomass, 3.2% hydro and 2.0% solar. Electricity consumption in 2010 was 603 TWh (production) - 60 TWh (assumed losses) = 543 TWh http://www.volker-quaschning.de/datserv/ren-Strom-D/index_e.php  
  • Hydro: At the end of 2010, about 4,700 MW of hydro was installed. Hydro energy produced was 19.5 TWh, or 3.2% of production. Hydro growth has been stagnant during the past 20 years. See below website.   As it took about $150 billion of direct investment, plus about $130 billion excess energy cost during the past 11 years to achieve 8.2% of total production from solar and wind energy, and assuming hydro will continue to have little growth, as was the case during the past 20 years (almost all hydro sites have been used up), then nearly all of the renewables growth by 2020 will be mostly from wind, with the remainder from solar and biomass. http://www.renewableenergyworld.com/rea/news/article/2011/03/new-record-for-german-renewable-energy-in-2010??cmpid=WNL-Wednesday-March30-2011   Wind and Solar Energy Depend on Gas: Wind and solar energy is variable and intermittent. This requires quick-ramping gas turbine plants to operate at part-load and quickly ramp up with wind energy ebbs and quickly ramp down with wind energy surges; this happens about 100 to 200 times a day resulting in increased wear and tear. Such operation is very inefficient for gas turbines causing them to use extra fuel/kWh and emit extra CO2/kWh that mostly offset the claimed fuel and CO2 reductions due to wind energy. http://theenergycollective.com/willem-post/64492/wind-energy-reduces-co2-emissions-few-percent  
  • Wind energy is often sold to the public as making a nation energy independent, but Germany will be buying gas mostly from Russia supplied via the newly constructed pipeline under the Baltic Sea from St. Petersburg to Germany, bypassing Poland.   GERMANY WITHOUT NUCLEAR ENERGY   A study performed by The Breakthrough Institute concluded to achieve the 40% CO2 emissions reduction target and the decommissioning of 21,400 MW of nuclear power plants by 2022, Germany’s electrical energy mix would have to change from 60% fossil, 23% nuclear and 17% renewables in 2010 to 43% fossil and 57% renewables by 2020. This will require a build-out of renewables, reorganization of Europe’s electric grids (Europe’s concurrence will be needed) and acceleration of energy efficiency measures.   According to The Breakthrough Institite, Germany would have to reduce its total electricity consumption by about 22% of current 2020 projections AND achieve its target for 35% electricity generated from renewables by 2020. This would require increased energy efficiency measures to effect an average annual decrease of the electricity consumption/GDP ratio of 3.92% per year, significantly greater than the 1.47% per year decrease assumed by the IEA's BAU forecasts which is based on projected German GDP growth and current German efficiency policies.
  • The Breakthrough Institute projections are based on electricity consumption of 544  and 532 TWh  in 2008 and 2020, respectively; the corresponding production is 604 TWh in 2008 and 592 TWh in 2020.   http://thebreakthrough.org/blog//2011/06/analysis_germanys_plan_to_phas-print.html http://www.iea.org/textbase/nppdf/free/2007/germany2007.pdf   Build-out of Wind Energy: If it is assumed the current wind to solar energy ratio is maintained at 3 to 1, the wind energy build-out will be 80% offshore and 20% onshore, and the electricity production will be 592 TWh, then the estimated capital cost of the offshore wind turbines will be [{0.57 (all renewables) - 0.11 (assumed biomass + hydro)} x 592 TWh x 3/4] x 0.8 offshore/(8,760 hr/yr x average CF 0.35) = 0.0533 TW offshore wind turbines @ $4 trillion/TW = $213 billion and of the onshore wind turbines will be [{0.57 (all renewables) - 0.11 (assumed biomass + hydro)} x 592 TWh x 3/4] x 0.2 onshore/(8,760 hr/yr x average CF 0.167) = 0.279 TW of wind turbines @ $2 trillion/TW = $56 billion, for a total of $272 billion. The feed in tariff subsidy for 9 years, if maintained similar to existing subsidies to attract adequate capital, will be about $150 billion offshore + $50 billion onshore, for a total of $200 billion.    
  • Note: The onshore build-out will at least double Germany’s existing onshore wind turbine capacity, plus required transmission systems; i.e., significant niose, environmental and visual impacts over large areas.   Recent studies, based on measured, real-time, 1/4-hour grid operations data sets of the Irish, Colorado and Texas grids, show wind energy does little to reduce CO2 emissions. Such data sets became available during the past 2 to 3 years. Prior studies, based on assumptions, estimates, modeling scenarios, and statistics, etc., significantly overstate CO2 reductions.  http://theenergycollective.com/willem-post/64492/wind-energy-reduces-co2-emissions-few-percent   Build-out of PV Solar Energy: The estimated capital cost of the PV solar capacity will be [{0.57 (all renewables) - 0.11 (assumed biomass + hydro)} x 592 TWh x 1/4]/(8,760 hr/yr x average CF 0.095) = 0.082 TW @ $4.5 trillion/TW = $369 billion. The feed in tariff subsidy, if maintained similar to existing subsidies to attract adequate capital, will be about $250 billion.   Reorganizating Electric Grids: For GW reasons, a self-balancing grid system is needed to minimize CO2 emissions from gas-fired CCGT balancing plants. One way to implement it is to enhance the interconnections of the national grids with European-wide HVDC overlay systems (owning+O&M costs, including transmission losses), and with European-wide selective curtailment of wind energy, and with European-wide demand management and with pumped hydro storage capacity. These measures will reduce, but not eliminate, the need for balancing energy, at greater wind energy penetrations during high-windspeed weather conditions, as frequently occur in Iberia (Spain/Portugal).  
  • European-wide agreement is needed, the capital cost will be in excess of $150 billion and the adverse impacts on quality of life (noise, visuals, psychological), property values and the environment will be significant over large areas.    Other Capital Costs: The capacity of the quick-ramping CCGT balancing plants was estimated at 25,000 MW; their capital cost is about 25,000 MW x $1,250,000/MW = $31.3 billion. The capital costs of decommissioning and restoring the sites of the 23 nuclear plants will be about $23 billion.   Increased Energy Efficiency: Increased energy efficiency would be more attractive than major build-outs of renewables, because it provides the quickest and biggest "bang for the buck", AND it is invisible, AND it does not make noise, AND it has minimal environmental impact, AND it usually reduces at least 3 times the CO2 per invested dollar, AND it usually creates at least 3 times the jobs per invested dollar, AND it usually creates at least 3 times the energy reduction per invested dollar, AND it does all this without public resistance and controversy.   Rebound, i.e., people going back to old habits of wasting energy, is a concept fostered by the PR of proponents of conspicuous consumption who make money on such consumption. People with little money love their cars getting 35-40 mpg, love getting small electric and heating bills. The rebound is mostly among people who do not care about such bills.
  • A MORE RATIONAL APPROACH   Global warming is a given for many decades, because the fast-growing large economies of the non-OECD nations will have energy consumption growth far outpacing the energy consumption growth of the slow-growing economies of the OECD nations, no matter what these OECD nations do regarding reducing CO2 emissions of their economies.   It is best to PREPARE for the inevitable additional GW by requiring people to move away from flood-prone areas (unless these areas are effectively protected, as in the Netherlands), requiring new  houses and other buildings to be constructed to a standard such as the Passivhaus standard* (such buildings stay cool in summer and warm in winter and use 80 to 90 percent less energy than standard buildings), and requiring the use of new cars that get at least 50 mpg, and rearranging the world's societies for minimal energy consumption; making them walking/bicycling-friendly would be a good start.   If a nation, such as the US, does not do this, the (owning + O&M) costs of its economy will become so excessive (rising resource prices, increased damage and disruptions from weather events) that its goods and services will become less competitive and an increasing percentage of its population will not be able to afford a decent living standard in such a society.   For example: In the US, the median annual household income (inflation-adjusted) was $49,445, a decline of 7% since 2000. As the world’s population increases to about 10 billion by 2050, a triage-style rationing of resources will become more prevalent. http://www.usatoday.com/news/nation/story/2011-09-13/census-household-income/50383882/1
  • * A 2-year-old addition to my house is built to near-Passivhaus standards; its heating system consists of a thermostatically-controlled 1 kW electric heater, set at 500 W, that cycles on/off on the coldest days for less than 100 hours/yr. The addition looks inside and out entirely like standard construction. http://theenergycollective.com/willem-post/46652/reducing-energy-use-houses
  •  
    Excellent, lengthy article , lots of data
D'coda Dcoda

Shortage in nuclear power workforce plagues China [28Oct11] - 0 views

  • A significant shortfall in nuclear power engineers and administrators is nearing a critical stage in China, with 27 new reactors under construction. Under Beijing's long-term project to increase the number of China's nuclear power plants, 6,000 new hires are needed each year in the nuclear power sector, but only several hundred college students who meet the job requirements graduate in the entire nation every year. Given that the July 23 high-speed train accident in Wenzhou that killed 40 people underscored China's inefficient system to train railway workers, concerns have also arisen that accidents could occur in a nuclear power industry lacking properly trained engineers and administrators. The shortage of workers in the nuclear power sector was reported by Chen Shaomin, professor of the engineering physics department at Tsinghua University, at the 2nd China International Nuclear Symposium, held from Oct. 20-22 in Hong Kong. The event was organized by the Chinese Nuclear Energy Association, a leading nuclear power industry organization in China.
  • The engineering physics department at the school has been designated by the government as a special division to train nuclear power personnel. Currently, 14 nuclear reactors are in operation in China, where about 14,000 engineers and administrators, as well as about 7,000 researchers, worked as of 2010. Twenty-seven new reactors are under construction--although approval of new construction projects has been suspended since the Fukushima No. 1 nuclear power plant crisis--while 33 prospective sites are awaiting construction approval from the government. According to Chen, 700 to 1,000 workers are required for each reactor. If all new reactors are built by 2020 as planned by the project, about 60,000 new recruits--which means 6,000 new workers each year on average--will be needed to keep reactors operational.
D'coda Dcoda

MIT Energy Series complains about nuclear power plant concrete but Wind Power four time... - 0 views

  • MIT Energy Initiative has a five-part series of articles that takes a broad view of the likely scalable energy candidates. The article on wind talked about the economics, the intermittent nature of wind power and prospects for scaling. The MIT article on nuclear power stated
  • Nuclear power is often thought of as zero-emissions, Prinn points out that “it has an energy cost — there’s a huge amount of construction with a huge amount of concrete,” which is a significant source of greenhouse gases.
  • Per Peterson analyzed that wind and solar use more steel and concrete than nuclear to generate the same amount of power
  • ...2 more annotations...
  • The MIT article on nuclear : The biggest factors limiting the growth of nuclear power in the near term are financial and regulatory uncertainties, which result in high interest rates for the upfront capital needed for construction. Nuclear power is half the cost in China and South Korea and almost as cheap in Russia and India. The countries with more favorable regulations is where nuclear power is being built. The IAEA list of nuclear reactors under construction. Country Number of reactors Nameplate watts Expected TWh generation China 27 27230 200 TWh Russia 11 9153 70 TWh S Korea 5 5560 44 TWh India 6 4194 32 TWh Taiwan 2 2600 20 TWh Bulgaria 2 1906 15 TWh Ukraine 2 1900 15 TWh Others 10 10000 80 TWh China and India are expecting to scale nuclear construction to several hundred gigawatts by 2030-2035.
  • China will start exporting reactors in 2013. Those reactors will be very affordable and middle eastern countries will be eager buyers and China will have no qualms about selling them nuclear power. The MIT article talking about lack of scaling of nuclear power before 2050 is talking about the USA and Europe building almost zero new power generation and having regulations and business which makes it expensive. I am surprised that MIT made such clear mistakes in their energy articles.
1 - 20 of 166 Next › Last »
Showing 20 items per page