The IFC's lessons of experience & the Chad-Cameroon oil and pipeline project (Bretton W... - 0 views
-
the ECMG committed a serious error in August 2004 when it provided the project with a certificate of compliance, certifying that the project had adhered to the environmental management plan. According to the ECMG, it had only found one level 3 non-compliance (the most serious non-compliance) which concerned the failure to protect archaeological sites, an area often considered to be of minor importance in the context of poor African countries.